Industrial Strength Stormwater Fix

A blue-collar business embraces a green stormwater fix.

by Lisa Stiffler

Editor's note 3/9: This profile is now available in PDF format here.

SLI%201.htmOn Seattle’s 8th Avenue South in the Georgetown neighborhood, empty school buses and recycling trucks rumble by. Semis squeeze past each other. Cars are parked on the street’s gravel shoulder amid shoe-soaking pools of muddy rainwater.

Georgetown’s busted streets and heavy-duty manufacturing plants seem like the last place where earth-friendly, sustainable stormwater solutions would take root. But this is the story of blue-collar industry partnering with a green-thinking community group to benefit them both. The trouble is, it was an unnecessarily long and challenging route to get the project done.

The century-old Markey Manufacturing Co. is a neighborhood institution, cranking out marine winches used to tow barges and haul anchors out of the sea.

But Seattle’s heavy rains were threatening to disrupt Markey’s operations by pocking the company’s driveway with gaping potholes, creating a perilous obstacle course for forklift drivers maneuvering their cargo.

“It was becoming a real safety issue,” said Bob LeCoque, Markey’s vice president. “We had a couple of loads drop off.”

The potholes are now gone, replaced with two paved driveways and three long, shallow ditches that catch the rain. The ditches, or swales, are lined with sand, soil, and plants that soak up the water.

When it rains, it puddles

Throughout most of Seattle, when the rain falls on roofs and streets, it’s shunted away by gutters and pipes. This area of Georgetown, however, is something of an anomaly; before the swales were built, there was no infrastructure to handle the stormwater and prevent flooding. When it rained, the water sat in puddles that took days or weeks to evaporate. Or it streamed over the industrial landscape into the nearby Duwamish River, carrying with it toxic pollutants and mud.

SLI%202.htm LeCoque wanted to pave Markey’s potholes, but city regulators opposed the plan unless something was done to address the potential increase in runoff that the paving could bring. LeCoque could lay hundreds of feet of pipe to connect with the existing King County stormwater system at the end of the street – at the cost of more than $1 million.

While Markey was trying to resolve its stormwater troubles, a community group comprised of nearby businesses, residents, local government employees, and others was working to improve the area through an effort called the Georgetown Riverview Restoration Project.The group teamed up with LeCoque to create a plan that was more environmentally friendly and cheaper than traditional stormwater infrastructure. They proposed what was essentially a large rain garden in the heart of one of Seattle’s grittiest industrial zones.

With help from Seattle’s Department of Transportation, Markey and the community group built three swales along the front of the Markey site, the largest stretching 60 feet long and 14 feet wide. The swales were dug about 2 feet deep, then refilled with 3 inches of soil and sand. The swales were ringed with wood chips and are still being planted with trees, grasses, and shrubs that can tolerate soaking wet soil in the winter and drought conditions in the summer.

“We’re trying to recreate what’s in the forest,” said Cari Simson, project manager with the Duwamish River Cleanup Coalition who helped lead the effort.“Obviously, we’re way removed from the forest.”

Innovative -- and slow going

SLI%203.htmThe innovative project – which is being hailed as Seattle’s first “industrial strength” natural drainage – is getting plenty of kudos now. But being the first of its kind, the project was tough to get done.

“It was a huge struggle,” said Shauna Walgren, a planner with Seattle’s Department of Transportation. There were months of meetings and countless questions about how it would work and what sort of precedent would be set.

“When you’re trying to do something different,” Walgren said, “the city doesn’t have experience to draw from."

Walgren helped coordinate between the multiple city departments involved and was key to getting approval for the plan, Simson said. The project, which started in 2007, was nearly derailed over concerns that the dirt to be excavated for the swales was contaminated with toxic chemicals. Fortunately, tests showed it wasn’t too polluted, and the swales were dug in October 2009.

Designing and excavating the swales close to $40,000, paid for by the Department of Transportation. The Georgetown Community Council working with the nonprofit Duwamish River Cleanup Coalition spent an additional $20,000 on soil for the swales, plants, designs, and other support. Markey Machinery paid roughly $35,000 to pave the driveways and add new sidewalks. Total bill? Under $100,000, a bargain compared to the price tag for a traditional stormwater system.

No more need for hip waders

Simson and others want to replicate the project in other industrial centers that also lack stormwater infrastructure, such as parts of Seattle’s South Park and SODO neighborhoods. As the Markey example shows, natural drainage can be a cheaper fix than building traditional pipes and stormwater holding tanks. Plus, it’s better for the environment because it re-greens areas with mostly native plants, and the swales and retention ponds actually clean the stormwater by allowing it to percolate into the ground.

But this kind of project won’t become more widespread unless the city makes it faster and easier to get approval for this sort of effort, said some of those involved. City departments – including Seattle’s Department of Transportation, Public Utilities, and Department of Planning and Development – need to work better together and make clear who is responsible for which decisions and permits, community members said. Even city officials said Seattle should create a standardized protocol for doing industrial projects like this one, and appoint someone to help a business navigate the process. Another way to encourage more industrial strength, low-impact development is through financial incentives -- grants, tax breaks, or a cut to utility bills -- for green stormwater solutions.

Before the swales and driveways were installed, Markey was a muddy mess in the winter and LeCoque was loath to host visitors. “The place looked like hell,” he said. That’s changed.

“I can walk from my car to my office without hip waders on,” LeCoque said. “We’re pretty proud of what we’ve done on the site here.”

Learn more about industrial stormwater fixes

The Duwamish River Clean-up Coalition and EOS Alliance are hosting a panel discussion and meeting about natural drainage projects in the Seattle area. It's free to attend, and here are the details:

  • WHEN: Wednesday, March 10, from 5:30 - 8:30 p.m.
  • WHERE: EOS Alliance Offices, 650 South Orcas St., Suite 220, Seattle
  • RSVP: Email bkantner@eosalliance.org, re: "Green Forum"

For more information, go to the Community Natural Drainage Forum website, or email Ben Kantner at EOS Alliance at bkantner@eosalliance.org or call 206-762-2553.


Photos of 8th Avenue South and the Markey Manufacturing Co. swales are used with permission from Laura Treadway.

This piece originally appeared on the Sightline Institute's blog, The Daily Score

Bookmark and Share


Comments

Welcome
Every one on internet searches for great content. Its very unfortunate with most of the websites published posts that are boring and out of context articles, just to show that new material is being published. Contrary to that immoral practice, this article is a great-written article.


Posted by: editor s picks from batteries1 net on 12 Aug 10

Hey..just want to let you know I appreciate your I and some of your posts? well..lol..not really many ones, but I like teh idea
Bye


Posted by: working homeschool moms on 17 Sep 10

Post A Comment

Please note that comments will remain open for only 14 days after the article is posted. While previous comments will remain visible, attempts to post new comments after this period will fail. This helps stop comment spam, so your forebearance is appreciated.

The Worldchanging comments are meant to be used for further exploration and evaluation of the ideas covered in our posts. Please note that, while constructive disagreement is fine, insults and abuse are not, and will result in the comment being deleted and a likely ban from commenting. We will also delete at will and without warning comments we believe are designed to disrupt a conversation rather than contribute to it. In short, we'll kill troll posts.

Finally, please note that comments which simply repost copyrighted works or commercial messages will be summarily deleted.

REMEMBER PERSONAL INFO?
Yes No

NAME


EMAIL ADDRESS


URL


COMMENTS



EMAIL THIS ENTRY TO:

YOUR EMAIL ADDRESS:


MESSAGE (optional):


Search Worldchanging

Worldchanging Newsletter Get good news for a change —
Click here to sign up!


Worldchanging2.0


Website Design by Eben Design | Logo Design by Egg Hosting | Hosted by Amazon AWS | Problems with the site? Send email to tech /at/ worldchanging.com
©2012
Architecture for Humanity - all rights reserved except where otherwise indicated.

Find_us_on_facebook_badge.gif twitter-logo.jpg